Sep 10,
2013 -
MARC has
affirmed its AA-IS rating on Kimanis Power Sdn Bhd's (KPSB) RM1,160.0 million
Sukuk programme (sukuk) with a stable outlook. The rating reflects an
anticipated base-load position of the project, a 285-megawatt (MW)
combined-cycle gas turbine power plant in Kimanis Bay, on the Sabah state's
electricity dispatch curve. Other credit strengths of the project include its
supportive long-term power purchase agreement (PPA) with a creditworthy
utility; standard, well-proven technology, limited fuel supply risk, as well as
60% ownership and substantial involvement of PETRONAS Gas Berhad (PGB).
Revenues from the PPA extend past the final maturity of the financing in 2028.
The rating
also incorporates the expected revision to the estimated commercial operation
dates (COD) for the project's three generating blocks stemming from schedule
delay in the construction of the 275-kilovolt (kV) transmission line from the
station to the main grid at Kolopis by offtaker Sabah Electricity Sdn Bhd
(SESB) based on the report by KPSB’s independent project management consultant
dated July 5, 2013. While the construction of the plant is slightly behind
schedule with physical progress at 97.46% against the planned progress of
98.21%, MARC understands that the contractor for the interconnection facilities
and communication facilities (IFCF) is expediting work on construction of the
IFCF. Also slightly behind schedule, construction on the gas pipeline between
the plant and the adjacent Sabah Oil and Gas Terminal (SOGT) is entering its
final phase and the pipeline is scheduled to receive its first gas by the
fourth quarter of 2013.
The
aforementioned developments are for now manageable at the 'AA-' rating level in
light of (i) provisions in the PPA allowing for deemed commissioning and
payment of the available capacity payment to IPP if IPP is not able to achieve
commercial operation date for the affected generating block on the scheduled
operation due to delays caused by the offtaker, which will provide sufficient
revenues to support the project's fixed costs including debt service on the
sukuk and mitigate the risk of foregone capacity revenues, (ii) possibility of
offsetting additional extension of time costs (including EPC costs and loss of
VOR payments) with potential financing/project savings, (iii) its cash-funded
finance service reserve account (FSRA) of RM18 million and project sponsors’
undertaking to provide cash deficiency support of up to RM50 million to fund
KPSB’s debt service requirements in addition to cost overruns support for up to
RM50.0 million during the construction phase.
MARC has
analysed a number of project delay scenarios which include a six-month delay in
COD and no energy revenues for 12 months. KPSB’s cash flow metrics are expected
to remain consistent with the rating under these two scenarios with minimum and
average finance service coverage ratios above 2.0 times and not less than 5.9
times respectively. Also providing protection to sukukholders during the
construction phase are the significant undertakings extended by project
sponsors to support debt servicing and cover construction cost overruns. Once
the project is in operation, it is expected to generate stable cash flows under
its long term power contract. MARC's cash flow analysis indicates good downside
protection under stress scenarios.
The stable
rating outlook reflects the strong economics of the project, very high sponsor
support, the comprehensive protection afforded by the provisions of the PPA,
and the expectation that the project will be completed within budget. The
rating could be negatively impacted if KPSB's actual CODs extend well beyond
the revised estimated commercial operation dates and result in a significant
weakening of its liquidity position. The rating may also be affected by plant
operational problems, a deterioration in the offtaker's credit profile or
changes in MARC's assessment of support.
Contacts:
Tan Eng
Keat, +603-2082 2265/ engkeat@marc.com.my;
David Lee,
+603-2082 2255/ david@marc.com.my.
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.